FDTC Cooling Tower Foundation
VALUE DELIVERED: MSI was given the opportunity to provide a price to a SC Technical College. We were able to provide the best price while meeting the clients scope and safety requirements.
CLIENT OBJECTIVES: Remove existing cooling tower foundation and install a new foundation for a new cooling tower.
SOLUTIONS: Due to design changes during the project, our civil department was required to pour structural concrete walls to support the new cooling tower. The original desgn was just for a foundation and steel supports. Our civil department was able to perform this work and support our mechanical and electrical departments in the installation of the new cooling tower.